When a data center OEM needed two custom lineups delivered as soon as possible, SEG's engineers and production team rallied to turn a 30-week project around in just nine weeks. Their dedication and expertise prompted the customer to order 30 additional units.
Demand for high-performance data centers is accelerating rapidly, driven by AI, cloud adoption, and real-time digital applications. This surge in infrastructure development is compressing build timelines and putting intense pressure on power system suppliers to shorten delivery cycles and be more flexible than ever.
SEG, a national manufacturer of custom low– and medium-voltage switchgear, is accustomed to designing, assembling, and shipping custom designs on accelerated timelines. So when a large electrical OEM needed to develop, assemble, test, and deliver two custom lineups for a data center application in just nine weeks, the SEG team accepted the challenge.

THE CHALLENGE
Both switchboards were engineered to support generator paralleling operations and included circuit breakers, busing, control systems, and wiring. In a conventional manufacturing cycle, a project of this size would take 30 weeks from design through delivery.
Instead of reworking the customer's design to fit SEG's in-house process, the team chose to adapt to it. Though this promised to accelerate delivery, it also introduced added complexity.
Inside, the OEM customer's application called for a slightly more complex switchboard design. Externally, it required a welded outer steel structure rather than SEG's standard bolted design, necessitating structural adaptations during fabrication. The assemblies also featured nonstandard enclosures and custom connection interfaces that introduced additional complexity and necessitated specialized logistics for transport.
"Basically, they were asking us to produce a more complex design within a much shorter time frame," said Gary Arnott, SEG's Chief Commercial Officer.
THE SOLUTION
Before SEG could even commit to a particular design path, it needed to confirm its production team could fulfill the labor hours required to assemble and test the lineups within the project's extremely compressed time frame.
The company understood that success could result in additional projects from the OEM and others in the data center sector, so it offered incentives to employees willing to temporarily move to a second shift. Eight volunteers were needed; 19 signed up.
"They were pretty energized after that meeting," said Corey Humbert, VP of operations at SEG. "Everybody wanted a copy of the design drawings, which we started handing out so they could review the specs before work even began."
Next, SEG's engineers reconfigured some structural parts of the OEM design to ensure that accurate fabrication and stamping could be done in-house. Most of the production team worked overtime over the next few weeks, often with the engineering team laboring alongside them to support progress.
Even with the design drawings as a roadmap and the circuit breakers supplied by the OEM, new challenges arose almost daily once work began. The welded outer structures required significant adaptations of parts and processes. The switchgear materials that the customer rushed to SEG lacked hardware, which needed to be delivered before assembly could proceed. Overnight orders for materials, hardware, and tools became so frequent that one employee was assigned to be a dedicated expediter tasked with coordinating logistics and retrieving packages.
"There's a lot of tribal knowledge that takes years to develop that doesn't always make it into the documentation," said Arnott. "Lineups like these don't go together like a LEGO set."
SEG made the copper and steel components itself, but variations in hardware or gaskets, for example, presented constant challenges. "Their design would call for one type of rubber that was different than the rubber we use," said Humbert. "There were doorstops and other details you wouldn't normally need to think about that would send us scrambling for another delivery."
Despite the constant surprises, pivots, and adaptations, the fabrication, assembly, and engineering teams made steady progress together. Before either switchboard was fully assembled, additional staff joined them, working elbow to elbow on the production floor to test components and perform quality checks on installed components.
THE RESULTS
The customer gave SEG nine weeks to assemble and ship two custom switchboards that would normally take 30 weeks to complete. SEG significantly exceeded the customer's expectations.
The OEM soon followed up with a request for two more assemblies to be shipped within a similarly tight time frame. SEG leveraged its hard-earned experience to complete those at an accelerated pace as well, which prompted the OEM to order 30 more lineups to be shipped over the course of several months. Fabrication now resembles more of an assembly line.
The fast turnaround on the first two switchboards established critical credibility — not only with SEG's customer but also among its employees. They had rallied together to assemble a custom design on an extremely truncated timeline and beat their own expectations. In the short term, that earned the production team a well-earned day off. Longer term, it showed the company that it had the personnel, expertise, and culture to meet challenges.
An agile supplier with decades of industry experience, SEG manufactures custom electrical gear on a fast cycle, but those two benefits don't often intersect. In this case, the company's size worked as an advantage, facilitating cross-functional coordination.
"Due to the nature of the request, the OEM exhausted a lot of avenues before we said yes," said Arnott. "We were the last call they made then, and now we're the first call."
Whether you need an accelerated schedule, a complex build, or both, SEG turns urgency into opportunity. Contact us to learn how we can help your electrical projects succeed on time, on spec, and within budget.